In the documentation there is a mode tag that can be added to a gantt view. This tag allows you to scale the time duration of the gantt view. But it doesn't seem to do anything in reality.

https://doc.openerp.com/trunk/server/03_module_dev_03/#id1

<gantt date_stop="date_finished" date_start="date_start" string="Productions" default_group_by="routing_id" mode ="month">
                </gantt>

This code isn't rejected as an XML error, but it doesn't seem to scale the gantt view.

How can you change the scale of a gantt view?

形象
丢弃

Do not works for me too : OpenERP 7

最佳答案

The below code is working in openerp 7

<record id="view_project_gantt" model="ir.ui.view">
    <field name="name">Project Gantt</field>
    <field name="model">project.test</field>
    <field name="type">calendar</field>
    <field name="arch" type="xml">
    <gantt date_stop="date_finished" date_start="date_start" string="Productions" default_group_by="routing_id" mode ="month">
        </gantt>
    </field>

</record>

    <record id="action_project_test" model="ir.actions.act_window">
            <field name="name">Project Test</field>
            <field name="res_model">project.test</field>
            <field name="view_type">form</field>
            <field name="view_mode">tree,form,gantt</field>     
    </record>
形象
丢弃
编写者

no it does not, the scale does not change. Try changing mode to day or 3weeks.

最佳答案
  1. List item
  2. List item
  3. List item
  4. List item
形象
丢弃
相关帖文 回复 查看 活动
2
2月 19
6753
3
2月 24
11791
0
3月 15
2260
4
1月 24
23251
2
1月 24
2552