Hello fellow forum users,

i have a question regarding quality check.

my current flow is

make manufacturing order -> produce -> manual action to transfer from  Stock to Quality Check -> Perform QC  -> manual action (return) to tranfers  from Quality Check to Stock.


lets say i produce 500 bottles, after manufacturing i want a QC for al these items. and then want to move the ones that passed the QC  back to stock location..  


in the QC check, 495 pass and 5 fail the QC check.


i want to move the 495 that passed to the stock location, and scrap the 5 that failed. so 495 will be added to the stock.


Is there a way to do this?