Hi there,

I'm starting to use the Project module of OpenERP 7.

Feeding the projects/phases/tasks with « Gantt View » starting and ending dates, I can have the Gantt view, but I can't find the zoom in/out options, which make this view somewhat useless.

Any hints ?

Kind regards,

頭像
捨棄

Same here, I am very intersting in this !

I have tried to update some view by adding mode="year" in the <gant section... But this had no effects.

Something like this would be very nice : http://acespritechblog.wordpress.com/2013/08/06/openerp-web-enhancement-in-gantt-chart/

How could we implement this ?

I'm very interesting in this too. Did you find something more to do that ?

最佳答案

Without any customize this view is not useable with real projects. I also test adding mode="week" or mode="day" but it seems to have no effects.