Can we hold the finished goods product for 1 - 2 days? So the material will be deducted from the stock, but the finished goods will be added to stock after 1 - 2 days.
For example:
I want to manufacture Product A, with material Product X, Y, Z.
So when I create the manufacturing order and execute it the product X, Y, Z will be deducted from the Stock, and after 2 days the product A will be increased. 
Is there any configuration to do that? or there is a module can resolve this problem?

Thanks!

頭像
捨棄
最佳答案

Have you considered multistep manufacturing? (2 step manufacturing)

This is where you pick items removing it from stock and moving it to separate pre-production location. 

Then a few days later when the manufacturing process is done the finished product is booked back in stock.

頭像
捨棄
作者

I see, I think we can do with multistep manufacturing.
Thanks!

作者

Bertus Kruger
I have another question for manufacturing module, is there any deviations report?
So, if the material to produce a product is 1 Unit, but when the actual manufacturing process the material needs 2 Unit, there's deviations for this manufacturing order.
Is there any recommendations for configuration for this?

Thanks!

This is about the closest I could get to a deviation report... https://apps.odoo.com/apps/modules/16.0/shvm_mrp_actual_vs_consumption/