Hello All, 

How to enable mrp scheduling of manufacturing orders on sales order line level? By standard the system is only looking to the sale.order header date. I tested some of the community modules where you have 'Requested date' on sales order line level but that did not impact to the mrp scheduler and manufacturing orders at all. 

Use case for Odoo v8 is simple: customer orders several products with different delivery dates and the manufacturing needs to be scheduled according to the product specific delivery date. Each product may have same or different total manufacturing lead time.

Appreciate your feedback.