Hi everybody,

When I run schedulers or reordering rules I get the same result : MO and PO (if it's necessary). So my question is which differences there are between both?

I seen that the first one work with the object named "procurement.order.compute.all" and the second one "procurement.orderpoint.compute".

Some people know something? Thanks for your support!

頭像
捨棄
最佳答案

Hello,

I think the run schedulers will do the job for all "allowed companies" of the user. And reordering rules will to the job for the only "current company" of the user ...


Hope this could help

頭像
捨棄
作者 最佳答案

Thank you Ahmed. Ok so if I have well understood, When you run schedulers all rules are performed. Hence, this is more important when you're in a multi companies configuration. Right?

Yes your answer help me a lot! Really :-)

頭像
捨棄

Yes I think it is important when you'r in a multi companies. don't forget to upvote if it helps ya ;)