We are in beginning stages of testing odoo and the mfg order capabilities. Poked around and could not find any settings to possibly help here.

I have setup a simple route code and assigned to a work order that is scheduled and I can see in gannt. below is simple flow

Prep

Paint

Install

QC


If I manually move an operation say paint...the successor operations install and QC stay put. In our current scheduling software if I move an operation all the successors follow suit as you cannot Install or QC till the prior operation is complete.


Is there a setting to force the successors to move when you make date changes?