Hey, 



I was wondering, is it possible to setup automatic flush of components that are linked to a specific operation? i.e. if operation A is linked to component X and Y, I wish when posting output in operation A to automatically consume components X and Y based on BOM quantities. This is key in our activities as some low-valued items (like labels etc.) should be flushed like that and it is very cumbersome to enter quantity for operator manually.


Thanks.