Hello,

I don't understand how is calculated the expected date in a sale document.

In the documents it is explained that this date takes into account the number of days of Purchase Delivery Lead Time but it doesn't seem to work.

The expected date is always the same, today's date.

Someone can help me?






Avatar
Abbandona
Risposta migliore

Hello,

for service and consumable products, SO take the minimum date (lead time) for order lines.

min date in this example (2days), Quotation date is 10/9/2022 --> Expected date should be 10/11/2022