Skip ke Konten
Menu
Pertanyaan ini telah diberikan tanda
1 Balas
4631 Tampilan

This workaround allows to reserve the work center for parallel operations without increasing the time reserved in the planning.

Ex : We have a work center in which we need 3 operations to run simultaneously, the total time for all the operations is 1 hour. 

With the standard configuration every operation is planned after each other:


Avatar
Buang
Penulis Jawaban Terbai

The objective is to book the work center for 1 hour instead of 3 hours. By artificially increasing the efficiency of the work center to 300 % we can mimic the parallel operation run :



Avatar
Buang
Post Terkait Replies Tampilan Aktivitas
1
Mar 24
7424
0
Jun 25
3499
1
Feb 23
3162
1
Sep 22
7813
2
Jan 23
5047