Skip to Content
Menu
You need to be registered to interact with the community.
This question has been flagged
1 Odgovori
4675 Prikazi

This workaround allows to reserve the work center for parallel operations without increasing the time reserved in the planning.

Ex : We have a work center in which we need 3 operations to run simultaneously, the total time for all the operations is 1 hour. 

With the standard configuration every operation is planned after each other:


Avatar
Opusti
Avtor Best Answer

The objective is to book the work center for 1 hour instead of 3 hours. By artificially increasing the efficiency of the work center to 300 % we can mimic the parallel operation run :



Avatar
Opusti
Related Posts Odgovori Prikazi Aktivnost
1
mar. 24
7464
0
jun. 25
3533
1
feb. 23
3184
1
sep. 22
7828
2
jan. 23
5063