Complete flow starting from a website order until the delivery of a product having a bill of material. (Key concepts : BOM - Operations - MTO route - Apply on variant - Consumed in operation - Manufacturing Lead Time - Customer Lead Time )
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Akuntansi
- Inventaris
- PoS
- Project
- MRP
Pertanyaan ini telah diberikan tanda
1
Balas
2578
Tampilan
Here is the use case :
Additional information about lead times (with MTO route).
=> In the configuration & flow video, +/- at 11:57s, the MO Scheduled date was "in 10 days" (30 days of customer lead time minus 20 days of Manufacturing lead time).
=>At +/- 16:57s, the Delivery Order Schedule Date was "in 30 days" from 05-August (creation date ).
Menikmati diskusi? Jangan hanya membaca, ikuti!
Buat akun sekarang untuk menikmati fitur eksklufi dan agar terlibat dengan komunitas kami!
DaftarPost Terkait | Replies | Tampilan | Aktivitas | |
---|---|---|---|---|
|
1
Apr 25
|
664 | ||
Customer Lead Time + Multiple Products Ordered
Diselesaikan
|
|
2
Jan 25
|
1166 | |
|
2
Mar 24
|
4660 | ||
How do you manufacture variants in 1 order?
Diselesaikan
|
|
2
Nov 21
|
2717 | |
|
1
Agu 25
|
1228 |