Complete flow starting from a website order until the delivery of a product having a bill of material. (Key concepts : BOM - Operations - MTO route - Apply on variant - Consumed in operation - Manufacturing Lead Time - Customer Lead Time )
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Účetnictví
- Sklad
- PoS
- Project
- MRP
This question has been flagged
1
Odpovědět
2585
Zobrazení
Here is the use case :
Additional information about lead times (with MTO route).
=> In the configuration & flow video, +/- at 11:57s, the MO Scheduled date was "in 10 days" (30 days of customer lead time minus 20 days of Manufacturing lead time).
=>At +/- 16:57s, the Delivery Order Schedule Date was "in 30 days" from 05-August (creation date ).
Enjoying the discussion? Don't just read, join in!
Create an account today to enjoy exclusive features and engage with our awesome community!
Přihlásit seRelated Posts | Odpovědi | Zobrazení | Aktivita | |
---|---|---|---|---|
|
1
dub 25
|
665 | ||
|
2
led 25
|
1171 | ||
|
2
bře 24
|
4670 | ||
|
2
lis 21
|
2727 | ||
|
1
srp 25
|
1231 |