Complete flow starting from a website order until the delivery of a product having a bill of material. (Key concepts : BOM - Operations - MTO route - Apply on variant - Consumed in operation -  Manufacturing  Lead  Time  -  Customer  Lead  Time )

Avatar
Zrušit
Autor Nejlepší odpověď

Here is the use case : 

Use case presentation

Configuration & Flow

Additional information about lead times (with MTO route).

=> In the configuration & flow video,  +/- at 11:57s, the MO Scheduled date was "in 10 days" (30 days of customer lead time minus 20 days of Manufacturing lead time).

=>At +/- 16:57s, the Delivery Order Schedule Date was "in 30 days" from 05-August (creation date ).