Přejít na obsah
Menu
You need to be registered to interact with the community.
This question has been flagged
5193 Zobrazení

Hi there, I think this is a bug but would like to confirm it. I started a project, and chose the time estimation on tasks in days. I create a tak estimated to 20 days work, then in the work summary I add a 16 hours time spent on it. Well the "Progress (%)" bar indicates 80%, clearly mixing days and hours.

I managed by switching to estimating time in hours but is there something I did wrong, or i that clearly a bug?

Avatar
Zrušit

I would say this is a bug - do you use long term planning? See bug https://bugs.launchpad.net/openobject-addons/+bug/1108913

Related Posts Odpovědi Zobrazení Aktivita
3
bře 16
5702
3
čvc 15
6457
1
bře 15
6658
1
čvn 23
3731
1
lis 22
4053