This question has been flagged
4871 Rodiniai

Hi there, I think this is a bug but would like to confirm it. I started a project, and chose the time estimation on tasks in days. I create a tak estimated to 20 days work, then in the work summary I add a 16 hours time spent on it. Well the "Progress (%)" bar indicates 80%, clearly mixing days and hours.

I managed by switching to estimating time in hours but is there something I did wrong, or i that clearly a bug?

Portretas
Atmesti

I would say this is a bug - do you use long term planning? See bug https://bugs.launchpad.net/openobject-addons/+bug/1108913