Dear all

I would like to use Odoo with tasks and subtasks but would like to restrict timesheet entries for subtasks only.

Could not find any way to do it with standard Odoo

any help is welcome

Regards


Maurice

Avatar
Zrušit

I know this question has been raised 5 years ago (& also answered). But I also would be interested in such a feature - is this anywhere in the pipeline?

Nejlepší odpověď

There is no option for disable timesheet on subtask using configuration.

but you can easily achieve it by a minor change in the XML view.
apply attrs  invisible on timesheet page when a task has a parent task