Ir al contenido
Menú
Se marcó esta pregunta
1 Responder
3559 Vistas

Dear all

I would like to use Odoo with tasks and subtasks but would like to restrict timesheet entries for subtasks only.

Could not find any way to do it with standard Odoo

any help is welcome

Regards


Maurice

Avatar
Descartar

I know this question has been raised 5 years ago (& also answered). But I also would be interested in such a feature - is this anywhere in the pipeline?

Mejor respuesta

There is no option for disable timesheet on subtask using configuration.

but you can easily achieve it by a minor change in the XML view.
apply attrs  invisible on timesheet page when a task has a parent task

Avatar
Descartar
Publicaciones relacionadas Respuestas Vistas Actividad
0
may 24
276
3
may 23
4177
1
oct 22
3182
0
nov 21
2112
1
may 21
2778