Hello,

I am using Odoo Community and I'd like to know if it is possible to add entries in a timesheet based on tasks not linked to a project?

Best regards;

Fadoua

頭像
捨棄
最佳答案

Hi Fadoua,

You have to set a project, as the Timesheet is activated based on Project not the task.

You can create a task without a project, but the Timsheet will not be available on the task unless it's related to a project, and the Timesheet is activated in the settings of this project.