Hello, how we can update the task/project progress in Odoo V.13?
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- Müşteri İlişkileri Yönetimi
- e-Commerce
- Muhasebe
- Envanter
- PoS
- Project
- MRP
Bu soru işaretlendi
You can do timesheet entries on tasks via activate "Task Logs" from settings menu. Or install hr_timesheet module and it will display Timesheet tab in tasks.
Also Progress bar in Kanban view which are in top of columns. It will calculate progress base on stage configuration. You can configuration your self from Configuration -> Stages. You can change progress using icon which is display in footer in kanban view for each record and right side in task from view.
Enjoying the discussion? Don't just read, join in!
Create an account today to enjoy exclusive features and engage with our awesome community!
Üye Olİlgili Gönderiler | Cevaplar | Görünümler | Aktivite | |
---|---|---|---|---|
|
1
Haz 23
|
3362 | ||
|
1
Kas 22
|
3639 | ||
|
1
Eyl 20
|
2736 | ||
|
7
Tem 20
|
4301 | ||
Cannot create task
Çözüldü
|
|
2
Haz 20
|
3848 |