When entering the MPS, i pressed on a hidden button with the shape of a "Bullseye" next to the Row "To Receive / To Supply / Produce " .

After clicking this button, it locked/greyed out the cells of this row. I clicked it several times to try and unlock the cells, however, now i have all 12 months locked and greyed out.

How can i unlock those cells to be able to set the min/max again.

P.S. i am working on a free trial online database.

Avatar
Vazgeç
En İyi Yanıt

When you click on symbol(Bullseye) it create that procurement on backend. This is the same as you click on launch green cells. The button create procurement for all and the icon on line generate procurement for that row/product only(Create MO/PO based on configuration).

Avatar
Vazgeç
En İyi Yanıt

Hi,

I can give you a solution but am not sure this is the right way.  Just go to apps menu and uninstall the module named Master Production Schedule ( technical name : mrp_mps ). Then just install it again.

Now you will be able to edit it.

Thanks