İçereği Atla
Menü
Bu soru işaretlendi
3613 Görünümler

Hi!

When we start the procurement manually (Version 7), the dates of all quotations are set to today.

But what we want is, to set the date to "start of production - delivery time - security days".

We don't want to fill our warehouse in next days (today + delivery time), when the production of the product is going to start in a year ...

Is it a bug or what are we doing wrong?

Thanks!

Avatar
Vazgeç
İlgili Gönderiler Cevaplar Görünümler Aktivite
5
Oca 24
12828
1
Mar 15
4591
4
Mar 15
29320
1
Mar 23
23587
1
Tem 16
11169