Pular para o conteúdo
Menu
Esta pergunta foi sinalizada
1034 Visualizações

I have a BoM to produce 100 units.

It takes 8 minutes to produce those 100 units.

For an order of 10,000 units, I expect it to take 8,000 minutes.


However, if I set the BoM > Operation > Expected Duration = 08:00. Then, Odoo gives me a work order for 80,000 minutes.


Note: the Work Center Capacity is set to 1.


I'm on Odoo 17. 


Also, please link to documentation... I could not find it.

Avatar
Cancelar
Publicações relacionadas Respostas Visualizações Atividade
1
jun. 24
1070
2
out. 19
4675
0
jul. 16
3599
1
set. 24
2013
1
ago. 24
2067