Skip to Content
Menu
This question has been flagged

I have a BoM to produce 100 units.

It takes 8 minutes to produce those 100 units.

For an order of 10,000 units, I expect it to take 8,000 minutes.


However, if I set the BoM > Operation > Expected Duration = 08:00. Then, Odoo gives me a work order for 80,000 minutes.


Note: the Work Center Capacity is set to 1.


I'm on Odoo 17. 


Also, please link to documentation... I could not find it.

Avatar
Discard
Related Posts Replies Views Activity
1
Jun 24
1099
2
Oct 19
4723
0
Jul 16
3620
1
Sep 24
2081
1
Aug 24
2122