Hi,


When i plan a task for 5 days, in calendar view filter per week i dont see it but in per month filter i see it

Anyone know why ?


Thank you.

Avatar
Buang
Jawaban Terbai

Hi,

In the odoo calendar view when you click on the filter dropdown the Week filter is available there

If it is not showing in your system, there may be something issue in your addons, Please try upgrading the base module, project module or calendar module.

Hope it helps

Avatar
Buang
Penulis Jawaban Terbai

Yes i know but am talking about calendar view of tasks

i cant see a task planned on many days in week filter

Avatar
Buang
Jawaban Terbai

Hi Kamel,

      The week filter already available in calendar view in odoo17 . Please check this screen shot . 