https://odoobooks.com/en/latest/manufacturing/subcontracting.html is about inserting a subcontracting process to "our" products.

Using the above example, let's say a subcontractor is receiving "sheets" of wood (from the client) and produces table tops. Another example is a bookbinder that receives 30200 printed sheets for the inside plus 1050 sheets for cover and finally produces 3012 books. Each sheet for cover contains 3 covers and each book contains 10 folded sheets.

Is there any corresponding doc about a company that does subcontracting? Company cannot use the materials from one client to produce something for another (obviously...). Company do not know from the beginning how many «table tops» are going to be produced. But an estimation should be noted and "highlighted" (example: About ~3150 books will be produced since the covers are only 3150, given or taken)

Avatar
Buang
Penulis

Please this post is about a subcontractor using odoo. Do not post answers about the subcontractor's client.

Penulis

@Mantavya Gajjar (mga) It does not solve the problem. The provided link is about Subcontracting for contractors (NOT for subcontractors).

Jawaban Terbai

Hello,

Please go through the video https://youtu.be/JPHB5_DiZfI, I have consider that what i have to produce as a contractor what i now in advance and based on that I will ask the raw material to supply to my customer. I have an opportunity to raise an bills for the contracting job-work based on the delivered items.

Let me know this solves your problem or not.

Avatar
Buang
Jawaban Terbai

Hi,

Have a look at this video and see whether it is helpful or not: Setup subcontracting in manufacturing process