We are using odoo 14 Ent, we can create tasks in project and will automatically appear in Field Service.


But, how do we get these tasks appear in Planning? I can't seem to find any linking field between these modules.


Thanks.


Avatar
Buang
Jawaban Terbai

Hi,

In the Planning app, as you hover over shifts or the planning board view, an icon will appear. This icon allows you to either create a new task or select an existing one. If you choose the latter option, a popup will open displaying all your existing tasks. From there, you can drag these tasks onto the planning board and rearrange them as needed.For more information, you can refer to our Blog Odoo 14 Planning.


Hope it helps

Avatar
Buang

Hi, t
hx for ur information. How to do that in V17?
I have create a project, task and subtask. On the task I add the planning role ... but I did't see the project and asl not the task in the planning APP.
Thx for help!