How can the project be linked to a sale order after creating the project?

Avatar
Muhammad Mahmoud

I created a project through the projects screen directly, can the project be linked to a sale order after creating it in this way, to be able to create invoices for customers with timesheet?

Avatar
Buang
1Jawaban
1
Avatar
Ibrahim Boudmir
Jawaban Terbaik

hi, 

you can still attribute a order line to the project and it will automatically be associated to the related order.

You only need to display sale_line_id if form view and attribute a line like this: 

hope this helps.

3Komentar
Avatar
Buang
Avatar
Muhammad Mahmoud
-

I try to link it this way, but the following message appears
"The operation cannot be completed: An FSM project must be billed at task rate or employee rate."

Avatar
Ibrahim Boudmir
-

It's because your project is a Field service Project.
check the constraint in python to see the related conditions for that message:

('fsm_imply_task_rate', "CHECK((is_fsm = 't' AND sale_line_id IS NULL) OR (is_fsm = 'f'))", 'An FSM project must be billed at task rate or employee rate.'),

Avatar
Muhammad Mahmoud
-

Thank you for replying, it is Done