I am using odoo v9e. How can I change task progress bar in basis of deadline.? Now, I am not using time sheet in project. So progress bar is empty. Any hint?
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Akuntansi
- Inventaris
- PoS
- Project
- MRP
Pertanyaan ini telah diberikan tanda
1
Balas
6429
Tampilan
Hi,
There is free community module "project life line for task" by Cybrosys Technologies. This module monitor deadline against total time for task & time now. Then the result will indicate life line of task in percentage like 95% or 54% etc. Please check the link below:
Hope it may help you. :)
Got It Neelmaar, Thanks for your reply and reference (y)
Menikmati diskusi? Jangan hanya membaca, ikuti!
Buat akun sekarang untuk menikmati fitur eksklufi dan agar terlibat dengan komunitas kami!
Daftar| Post Terkait | Replies | Tampilan | Aktivitas | |
|---|---|---|---|---|
|
|
0
Jun 23
|
2995 | ||
|
|
0
Sep 25
|
2516 | ||
|
|
2
Mei 25
|
3325 | ||
|
|
1
Des 24
|
6630 | ||
|
|
3
Agu 24
|
7416 |