we have automated action to create activity (Action To Do = Create Next Activity) when a new lead created by user this will create activity for next day by default  (date_deadline).

is there any setting to create activities for today's date only? or some other way?

please help.

note: i am not allowed in this task to use a custom module.

regards



Avatar
Buang
Penulis Jawaban Terbai

it has been done by setting Due Date in = 0  Days in Automated Actions