Skip ke Konten
Menu
Pertanyaan ini telah diberikan tanda
1 Balas
5019 Tampilan

In my v7.0 environment, when I record the time through Human Resources -> My Current Timesheet choosing an analytic account, analytic journal items are generated but with no costs (even though I have assigned a service item with cost price to the employee), while it does recognize costs when I enter the time through Projects -> Timesheets. Why are the behaviors different?

Avatar
Buang

I guess it needs to be approved in my current timesheet. This is not the case in Timesheet Activities.

Penulis Jawaban Terbai

Just found out that the cost is recognized in analytic account for the hours input via My Current Timesheet function (even before approval) in Version 7.0-20130717-231254. I guess there was a bug in older version.

Avatar
Buang
Post Terkait Replies Tampilan Aktivitas
7
Jun 17
10870
2
Jul 16
4603
2
Mar 15
6068
1
Mar 15
7510
0
Mar 15
3630