I am looking for a way whereby you can shift a work order under "Manufacturing Orders - Order Planning" in the calendar view into a different month. It works nicely when the calendar view of this month doesn't end on the Saturday of the last day of the month. The first days of the next month are then already displayed and you can just move them across.

However how does it work when the first day of the next month is not displayed? How do you move a work order into the next month then (e.g.: April 2016 - Saturday fell on the 30/04/2016).


Avatar
Buang
Jawaban Terbai

The process is not as nice as the drag feature, found in the calendar view; but, you can edit the start and finish dates inside the work order form.

  1. Click on the work order 

  2. Select 'Time Tracking' tab

  3. Edit 'Planned Date' start and end

Hope this helps.