Hi every body ...

I need to setup BOM with some items which not depends of the real quantity to produce on the work order :

i.e. : For Each work order, I need to do :

- Produce the requested quantity of final item from BOM
- Produce an extra item once per Work Order.

This is in the aim of making quality control by work order session.
For example, making "X" amount of a  product and then adding "Y" items for quality sampling, not depending of the real value of "X".

If someone can help ...

Thanks in advance

Avatar
Buang
Jawaban Terbai

Add this product to the Bill of Materials with a quantity of 0, allowing users to choose the quantity on each Manufacturing Order actually used.

UNLOCK the Manufacturing Order to modify quantities if there are more needed to be consumed.