Skip to Content
मेन्यू
This question has been flagged
1 Reply
5029 Views

I would like to know if OpenERP 7.0 supports Critical Path Monitoring (CPM). If yes how? Can you point me to a reference?

Tnx.

Avatar
Discard
Best Answer

You can do that with the community modules "project_time_sequencing" and "project_time_scheduling"

Avatar
Discard
Related Posts Replies Views Activity
1
मार्च 15
5776
2
मार्च 15
10281
0
मार्च 15
3916
0
मार्च 15
5142
1
मार्च 15
5063