I would like to know if OpenERP 7.0 supports Critical Path Monitoring (CPM). If yes how? Can you point me to a reference?

Tnx.

Avatar
Descartar
Best Answer

You can do that with the community modules "project_time_sequencing" and "project_time_scheduling"