Good morning, 




Please help me with the following question: 




In the workshop module that connects to the manufacturing module, When I already have my workplaces and I will create a manufacturing order and configure the same that has to go through certain workplaces, how can I make some workplaces work at the same time the manufacturing order as they do not depend on each other ?

Avatar
Zrušit
Nejlepší odpověď

Odoo is set up that first work order must be finished, before you can start the next.  But if you only remove the filter that say "Ready" or add "Waiting" the next work order is visible and you can start working on it.