Hi,

I'm using MTO to purchase products based on sales orders and cash them in in POS.

The flow is like this:

Create SO with product with MTO and buy> confirm SO > generate auto PO> confirm PO> settle order in POS> it creates a new PO linked with POS....even if I receive the products from PO generated from SO, I can't deliver them because the delivery is done from POS and it's linked to the PO generated from there.

I need to be able to settle the order in POS and deliver from there the products received from the PO linked to the SO.

Hope you understand my need an can offer a solution.

Thank you!

Raluca

Avatar
Zrušit
Autor Nejlepší odpověď

No, I need to order the products only if the client orders, I don't have stock on them. But thank you!

Avatar
Zrušit
Nejlepší odpověď

If I understand right: You have 2 sales orders. The it do create two purchase orders with MTO.

You might have a better process if you not use MTO, but use reordering rules with min QTY = 0.  It will work about the same way, but needs to run a scheduling job to create the purchase order.