Přejít na obsah
Menu
You need to be registered to interact with the community.
This question has been flagged
1 Odpovědět
3046 Zobrazení

In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.

I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?

Avatar
Zrušit
Nejlepší odpověď

In effect what you trying to achieve is to change the 'scheduled date' of a MO. You can drag and drop to change it while on the calendar view of Operations > Manufacturing Orders menu

By doing so it does change the MO to an unplanned state.

Avatar
Zrušit
Related Posts Odpovědi Zobrazení Aktivita
1
kvě 25
1362
2
čvn 23
2746
2
srp 22
4850
1
bře 22
2654
1
úno 22
2448