Přejít na obsah
Menu
You need to be registered to interact with the community.
This question has been flagged
2 Odpovědi
9085 Zobrazení

Hi All!

The situation is the following:

I have two different raw materials: Raw1 >> diameter 65 mm Raw2 >> diameter 63 mm

P1 diameter 60 mm P2 diameter 64 mm

My product( P1) diameter is 60. So in this case I can create my P1 from Raw1 and Raw2 also. When we create the sales order we do not know exactly what Raw material is in our Raw mat. Supplier. So sometimes we use Raw1 and sometimes Raw2. (That's why I cannot use 2 BOM one for Raw1 usage one for Raw2 usage and select it before order) Sure some other products (P2) we us exactly the Raw1 because the Product diameter is 64.

So haw can I handle this situation? I am afraid I have to create a new module what is inherit the procurement, for the alternative material usage. Somebody already did something like this? If yes what is the best way to modify the procurement. (New work flow step...or what...)

Avatar
Zrušit
Nejlepší odpověď

If I change the raw material how can I calculate the real cost of the product?

Avatar
Zrušit

It really work but I need flexibility in the production order to change the bom or if a product would scraped the cost must be add to the prodcution.

Nejlepší odpověď

Perhaps you can look at https://www.openerp.com/apps/7.0/mrp_change_rm/

It may be easy to get it working with 6.1.

Avatar
Zrušit
Related Posts Odpovědi Zobrazení Aktivita
0
dub 15
10075
0
bře 15
4433
0
kvě 16
3721
2
bře 15
5209
0
lis 17
3477