İçereği Atla
Menü
Bu soru işaretlendi
1 Cevapla
509 Görünümler

When producing a milled part for example, i create a BOM with the raw material and the work orders like "writing NC-program" and "milling". But as the program writing doesn't need to be done more than once per product, i dont want the work-order-time to be multiplied with the number of products as soon as i create the manufacturing order out of it. What can i do?


Avatar
Vazgeç
En İyi Yanıt

I think you should set a quantity in the bom.

Avatar
Vazgeç