dear all,

hope you are very well!

am wondering on routing configuration for raw material.

3 raw material makes one finish good

each raw material store on different location in same warehouse

raw material 1, location;     WH/A/2

raw material 2, location;     WH/B/3

raw material 3, location;      WH/C/4

when call from finish good route, their is only one manufacturing location, 

i have tried push rules, but they are not giving full tracebility.

how i can solve this

many thanks.

Avatar
Vazgeç
En İyi Yanıt

I think this is not possible by default your manufacturing always MTS.  So only possible if you change your "Supply Method" as MTO in your stock moves.(you can also create some server actions that will do this for you for some specific condition).

Avatar
Vazgeç
Üretici

true; but with MTS or MTO, in both conditions, product call is only from one material location. how i can make different call from three material location for manufacturing.

That is possible by creating routes/procurement rules for that procure locations. Those rules are only triggered if we have supplied method as an MTO.