I have a question regarding manufacturing at other Vendors. Here is the process that I am trying to recreate. I have grain which some is bought some is harvested, then this grain will be milled at another company and the milling will have a cost of milling and packaging. Then I have the final product the flour in bags.

I am able to create the manufacturing for the flour with the cost included, but it doesn't record the sending of the grain and receiving of the flour. Does anyone have a similar use case?   

Avatar
Vazgeç
En İyi Yanıt

Look at this: MRP - Manage your Subcontracted Production in Odoo​

The vide is a few years old, but I think it is still the same.  The product you send to vendor must be stockable. Which means you cannot have have subcontracting as an operation in the middle of a single level manufactuirng order. You must set it up as Multi level. 

Goods receipt is done with comfirming the subcontracting manufacturing order.  

It has been announced improvement for subcontracting in V13. Looking forward to that.