I notice that in my Manufacturing orders. The reserved amount of materials is always 8% more than the amount specified in my BoM ... 


Where is that configured ?


I cant find any information about it in documentation.


Avatar
Vazgeç

Never happened to us or heard anything similar. How does this happen? Do you have any modules installed? Customs?
More info will be great.

Üretici

i have no clue why it happens, i have filed a bug, having isolated the issue on a staging instance.

No custom modules that touch these areas of code.



Üretici En İyi Yanıt

Ok i found the issue

So a BoM itself also have a UoM ... and that one was 8% smaller (panels of xx sqm) than the UoM of the product the BoM was for.

Making them in sync fixed it.

Avatar
Vazgeç
En İyi Yanıt

Hello,

You have to check your costing method strategy.

shivoham.odoo@gmail.com

Avatar
Vazgeç
İlgili Gönderiler Cevaplar Görünümler Aktivite
0
Oca 25
1126
1
Haz 25
4945
0
Şub 19
4061
0
Kas 18
3428
0
Şub 16
4040