If I create product Boat with bill of materials, one of BOM is Dashboard, and Dashboards also has it's own BOM

I created Reordering rules for Boat and Dashboard

When I create sales orders with 2 Boats, then click on buttong "run reordering rules", it will create only one manufacturing order which is for Boat, if I click again on the button,it will create manufacturing order for Dashboard

Why it didn't create 2 MOs from the first click on Run reordering rules? Am I missing something?

Avatar
Vazgeç
En İyi Yanıt

Hi Alaa and fasluca, I'm not sure on the difference between menus "Run schedulers" and "Run reordering rules" can you explain me?

Twice, It's possible to set a reordering rules on a "finished product" with route set to "Manufacture" and when a run it's completed, PO (RFQ) and MO are created based on BOM of the finished product?

Avatar
Vazgeç
En İyi Yanıt

Hi Alaa,

I think its better to use 'Just in time scheduler' for this process.

have a look at these videos

  • https://youtu.be/eR_IQcuR5c4

  • https://youtu.be/BkgjyHUdjhQ

Avatar
Vazgeç
Üretici

The only reason that I'm not using this approach is that it's not merging similar manufacturing orders, if I create sale order of 2 Boats and 5 Dashboards (yes I can sell dashboards separetly) , the system will create 3 manufacturing orders : 2 boats , 2 Dashboards , 5 Dashboards. From a manufacturing perspective, I should see 2 MOs only: 2 boats , 7 Dashboards. This is not possible with Just in time scheduler as I found out, but it's working if I use reordering rules, the problem is I have to click 2 times on "run reordering rules" to generate 2 MOs as in the example here which is annoying