We want to check the RFQ before we confirm them, so if the trigger is on the same day as we are sending out we don't have enough time.

How can we generate the RFQ and all the MO created from another MO or a SO?

Thank you.

Avatar
Vazgeç
Üretici

Based on this article it seems in Odoo 14 this would not be possible... without customs?
https://odootricks.tips/odoo-14-replenishment-mto/

En İyi Yanıt

question. you have products with buy+mto. or manufactory wich has manufactory+mto routes.
so if product is purchase able you will get RFQ. when you do not get it?

Avatar
Vazgeç
Üretici

Forgot to mention! We are not using MTO, only MTS.

So when we are confirming a MO or SO if the date is for today or tomorrow eveything triggers, but if it is on a future date it does not trigger. We would like it to trigger independently of the date.
Thank you.

by default(do not know what version you use), but it is MTO(repleanish on order). sujest to activate. so after that, all MO/SO will create depending RFQ and allways plus before you confirm RFQ

Üretici

We are on Odoo 14, but we would like to keep using MTS as we want to work with stock, not make to order.
MTS (replenishment rules) also create RFQ and other MO, but the problem is with the date...

Üretici

After some investigation your answer was the right one. We can't do that with MTS, it can only be done with MTO.