first cutting then switching then packing a product 


my product face many department to make an final product how i can handle that department in odoo v13 ? 

1 - cutting department

2 - switching department

3 - packing department 

then final product how i can handle it ? 

thanks in advance 


Avatar
Vazgeç
En İyi Yanıt

Hi,

Use the concept of the work order and work centers. You can activate it from MRP settings and set the routing for the bill of material of corresponding product.

For more see: https://www.odoo.com/documentation/user/13.0/manufacturing/management/manufacturing_order.html