İçereği Atla
Menü
Bu soru işaretlendi
1 Cevapla
6469 Görünümler

Hello,

In project management module if I am close the project than I am creating task on project OpenERP allow to create task.

Is this right to allow creation of task on close project?

And if allow than what is the purpose of it?

Thanks

 

 

Avatar
Vazgeç
En İyi Yanıt

Hi Solanki,

I have also faced same situation, inspite of closing the project we can create tasks and issues, etc for that project. So, what I did is 

1) hided the buttons(Task, Issues, etc) on project form, once it reaches to the dead state by applying attrs on buttons div.

2) at task, issue, milestone, etc masters on project_id field applied the domain ('state', '!=', 'closed').

3) Rest wherever u get the project_id field(related to project master) apply ('state', '!=', 'closed') domain .

Now i cant create the tasks or issues or anything from any scenario.


thanks

Avatar
Vazgeç
İlgili Gönderiler Cevaplar Görünümler Aktivite
1
Haz 23
3399
1
Kas 22
3694
2
Haz 20
3892
2
Tem 18
7419
4
Tem 18
8256