Hello everyone. my client manufacture plumbing fittings. the production process is like this:

A - raw material is brass rod

B- cutting : small Pieces

C- forging : Forged part

D- Machining : Finished part

 I am facing a problem to configure BOM, because BOM works like : A + B = C. But in our case, if I start a production order of Finished part D I need Odoo to automaticaly Start a production order Of B an C, 

Thanks in Advance

Awatar
Odrzuć
Najlepsza odpowiedź

In odoo v14, Create a BOM by going to the manufacturing module under "Products". Enter the name of the product. Below add the components or raw material that you need to create the particular product like in above case Raw material is Brass rod. On the right side of components, you can add operations like in this case Operations are Cutting, forging and machining. You can specify the time each operation takes or odoo can automatically compute the time according to the previous work orders. You can start or end any operation at any time or you can start more than one operation at a time. For example : If u want to start C operation for the products which have already completed the previous operation. The next operation will not start automatically.

Hope this helps..


Steffy

Junior Odoo consultant

Tel: +353 1 886 5684 (IE) +44 121 285 5684 (UK)  +91 964 381 7554 (IN)

 

Target Integration | CRM ERP Cloud

Website | LinkedIn | Twitter | Facebook | YouTube | Instagram

Awatar
Odrzuć
Powiązane posty Odpowiedzi Widoki Czynność
1
wrz 24
1694
0
sie 25
286
0
sie 25
220
2
sie 25
817
0
lip 25
558