I have created a project template with tasks having set start and end dates. When I create a new project from the template - the task dates are not copied. Ideally the dates should be copied and if the project start / end dates are altered, the task dates should be scaled accordingly. Or am I doing something wrong?

아바타
취소

Please post which version (6.1,7,8,9,10,11) and Edition (Community, Enterprise) of Odoo your question relates to as the answer may be different depending on one or both.