how to calculate  Scheduled Date   in delivery date in odoo 11

how to depend customer lead time ,manufacture lead time and delivery lead time affect how  Scheduled date in delivery order

please help

thanks in advance



아바타
취소

Hello stephen,

What problem you are getting to calculate scheduled date can you give any example? because when you add sale order line it ask you for lead time in days, which you can add and let say if you add more than one line of SO. so minimum lead time will be taken into commitment date of SO and that date will go into deliver order.

hello,

schedule date into DO is calculated based on SO commitment date. and SO commitment date is calculated based on minimum delay Date from SOL.