During Project Management meetings, we review all Tasks for each Project.


We want an quicker way to check off completed Tasks than to drag them via the Kanban, because we actually use the List View and have added additional columns to help us complete the review process.


I'd like a checkbox that can allow us to complete Tasks with a single click:



아바타
취소
베스트 답변

This method will work as long as "DONE" is the same stage in every Project:


1. Create a Server Action that sets the status:



Make a note of the ID of this Server Action (find it in the URL) so you can use it in the View below.  In this example database it was 679.


2. Create a View that inherits the underlying Task List View and adds the button, hiding it when the Task is done:



This gives Users this kind of User Experience: